Steel Hub

Beam tonnage is calculated by multiplying the correct section’s mass per unit length by its length and quantity, then converting the result into the required ton unit. For a chart expressed in kilograms per metre, the calculation is: tonnage in metric tonnes = kg/m × length in metres × number of pieces ÷ 1,000.
The arithmetic is straightforward. The larger risks are selecting a similar-looking but different section, mixing metric and imperial units, or treating finished-member tonnage as the quantity of stock steel that must be purchased. A reliable estimate keeps section identification, net material requirements, and purchased quantities separate.
An H-beam and I-beam weight chart provides nominal mass per unit length for defined sections. It does not provide a universal weight for every beam of the same depth. Two sections described as “200 mm beams” can have different flange widths, web thicknesses, flange thicknesses, and therefore different weights.
Before taking a value from a chart, match the drawing or material schedule against:
HEA 200 and HEB 200 illustrate why the series matters: they are not interchangeable weight entries. Likewise, an American W-section should not be replaced in a takeoff by a metric H-section merely because the outside dimensions appear close. Any structural substitution requires separate engineering approval.
For welded or otherwise custom-fabricated beams, a standard rolled-section chart may not apply. Use the specified plate dimensions and fabrication details, or an approved calculated unit mass. Steel grade alone is not a reason to select a different chart row; the defined section geometry remains the starting point.

Section tables contain several numbers that can be mistaken for weight: cross-sectional area, moments of inertia, section moduli, and radii of gyration. Locate the column explicitly labelled mass per metre, unit mass, kg/m, or its imperial equivalent. Do not use a number simply because it appears next to the designation.
Common published nominal values include 42.3 kg/m for HEA 200 and 42.2 kg/m for IPE 300. These values belong to those specific sections; they are not general values for H-beams or I-beams. Confirm the entries against the catalogue accepted for the order.
If a chart gives cross-sectional area but no unit mass, a useful check for ordinary structural carbon steel is:
Unit mass in kg/m ≈ cross-sectional area in cm² × 0.785
This uses a nominal steel density of 7,850 kg/m³. An area of 53.8 cm² therefore gives approximately 42.2 kg/m. The area must include the actual section geometry, including rolled fillets where applicable. Calculating a rolled beam as three simple rectangles omits those fillets and can understate its mass.
Use this relationship to investigate an apparent mismatch, not to replace an authoritative section-table value with a rough dimensional estimate.
For a metric takeoff, each line needs the section designation, unit mass, cut length, and piece count. Where the same section has several lengths, retain separate lines so revisions and cutting requirements remain traceable.
Line mass, kg = unit mass, kg/m × individual length, m × quantity
Total metric tonnes = sum of all line masses, kg ÷ 1,000
The following illustrative schedule uses nominal section-table weights. Lengths and quantities are example project inputs, not standard supply lengths.
The first line is 42.3 × 8 × 24 = 8,121.6 kg, or 8.1216 metric tonnes. Adding all three lines gives 17.748 metric tonnes of nominal beam material at the scheduled lengths.
That description matters. The result is not automatically the purchase tonnage, the shipping weight, or the finished fabricated assembly weight. It excludes additional stock length and any plates, stiffeners, cleats, bolts, weld metal, or coatings not separately included in the calculation.
In a spreadsheet, if unit mass is in column B, length in column C, and quantity in column D, the line-tonnage formula is =B2*C2*D2/1000. Keep sufficient precision in the calculation and round the displayed project total only after summing the lines. Rounding every small line to two decimal places can create an avoidable cumulative difference.
In international quotations, the word “ton” is insufficiently precise. A metric tonne is 1,000 kg; a US short ton is 2,000 lb, approximately 907.185 kg; and an imperial long ton is 2,240 lb, approximately 1,016.047 kg. State the required unit explicitly on the takeoff and quotation comparison.
If the chart uses pounds per foot, either calculate entirely in imperial units before converting, or convert the unit mass before multiplying by metric lengths:
kg/m = lb/ft × 1.48816
For example, W12×26 denotes a W-section with a nominal weight of 26 lb/ft; the “12” represents its nominal depth family, not an exact depth measurement. Ten pieces at 20 ft each give:
26 × 20 × 10 = 5,200 lb ≈ 2,358.7 kg = 2.359 metric tonnes
Do not multiply 26 lb/ft directly by a length entered in metres. Similarly, a metric drawing length of 6,000 mm must become 6 m before multiplying by kg/m. Explicit unit labels in spreadsheet headers are more reliable than expecting every contributor to infer the intended system.
A schedule of finished members measures the material required at the specified member lengths. Purchasing full stock bars introduces another calculation: how many bars are needed to produce those members after allowing for saw cuts, end trimming, and usable remnants.
Suppose 20 members are required at 5.8 m each, and the selected supply length is 12 m. Two members fit within one stock bar, subject to the cutting allowance. Ten bars are therefore required:
At 42.3 kg/m, the finished-length quantity is 4.9068 tonnes, while the purchased stock quantity is 5.076 tonnes. The difference is 0.1692 tonnes, or approximately 3.45% of the finished-length mass. This percentage comes from the cutting arrangement; it is not a general waste allowance for beams.
Length compatibility is more important than a blanket percentage. Two nominal 6 m members should not automatically be assigned to one nominal 12 m bar: saw kerf, required end preparation, and available length tolerance can prevent both finished pieces from being produced. The supply-length agreement must support the cutting plan.
Reusable remnants also need distinct treatment. They increase the mass purchased for the current order, but are not necessarily scrap. Identify whether they will be used elsewhere, retained as inventory, or discarded. Otherwise, a project can record the same residual steel as both a full project cost and usable stock without a consistent accounting basis.
If cutting optimization is not yet available, show any provisional allowance separately from net beam tonnage. Replace it with the bar-by-bar requirement once supply lengths and fabrication details are settled.
A weight-chart calculation produces theoretical mass based on nominal section properties. Delivered steel can differ because of dimensional and mass tolerances, actual supplied lengths, and the items included in the shipment. A difference between calculated and weighed mass does not, by itself, establish a supply error.
The commercial question is whether invoicing is based on theoretical mass or actual weighed mass, and how that basis is defined in the purchase agreement. For theoretical billing, align the section catalogue, unit mass, billable lengths, and rounding convention. For actual-weight billing, establish the weighing method and treatment of packaging or transport tare.
A practical reconciliation follows the source of each difference:
Do not apply an assumed universal tolerance percentage to explain a discrepancy. Acceptance limits depend on the applicable product requirements and purchase terms. Check the governing documents before deciding whether a difference is acceptable.
For a steel budget, multiply the agreed billable tonnage by a price expressed in the same ton unit. Keep cutting charges, fabrication, surface treatment, freight, and other separately quoted costs outside that multiplication unless they are explicitly included in the rate.
For delivery planning, purchased stock mass is a better starting point than finished-member mass when full bars are being transported. Shipment planning must also account for other cargo, packaging, dunnage, and vehicle or route restrictions. A project-wide tonnage total cannot show whether an individual delivery is suitable.
Likewise, chart weight can support an initial member-mass estimate, but it is not a complete lifting assessment. Added connections, lifting equipment, geometry, and the approved lifting arrangement require separate consideration.
The most useful final record therefore preserves three clearly labelled quantities: net scheduled beam tonnage, stock purchase tonnage, and the agreed delivery or billing weight. Keeping those figures distinct makes the weight chart a dependable control tool rather than a source of apparently conflicting totals.
Please give us a message
Tianjin Kaichuang Metal Material Co., Ltd
Add: No. 41, District 6, First Street, Huanghuadian Town, Wuqing District, Tianjin
Tel: + 86 137 9101 9833
E-mail: boss@kaichsteel.com